Procedure For Getting A Sprinkler Meter
The following is the typical procedure that you should follow if
you are interested in purchasing the use of and installing a sprinkler
meter:
- Obtain a Plumbing Permit – Plumbing
permits are purchased from our Building Department at Township Hall, which
is located at 3040 North Prospect Road (at Cherry Hill and Prospect Roads).
For more information about plumbing permits, call 734-482-6099 and request
to speak to someone from the Building Department.
- Separate Plumbing – Using the
Sprinkler Meter Installation Diagram (see below) as a guideline, you (the
customer) will need to arrange to have all plumbing associated with the
secondary meter reconfigured so that it is limited to usage outside of the
home only (hose bibs and underground irrigation systems)
The diagram depicts a ¾” meter installation, which is the correct
size meter for a sprinkler system having continuous flows of a maximum of
15 gallons per minute. This size meter is the one that has typically been
installed, to date, in all of the Superior Township subdivisions east of
Leforge Road and south of Geddes Road.
-
Pay for Meter and Schedule Installation –
Once the plumbing has been separated, contact us at 734-480-5500 to
arrange to pay for the use of the meter and the installation and to
schedule an appointment for us to install the meter.
The fee for the use of a sprinkler meter is $250.00 for the meter
and $30.00 for the Utility Department’s portion of the installation, for a
total of $280.00. This fee is based on the size meter that is correct for
a sprinkler system having continuous flows of a maximum of 15 gallons per
minute as mentioned in item #2 above.
Our Technicians are available, by appointment only, to install these
meters on Tuesdays and Thursdays, between the hours of 9:00 a.m. and 3:00
p.m.
Please
click here to view/print the Sprinkler Meter Installation
Diagram.
Please
click here to view/print the Sprinkler Meter Policy.
This is printed from: http://twp-superior.org/departments/sprinkler_meters_procedure.html
on Feb. 7, 2012 2:39 pm
|